Guidance: Project Adjustment Requests

The Department has delegated some decision-making on PARs to Town Deal Boards and Local Authorities. This allows places to modify the agreed spend, outputs and outcomes against any project by up to 30% without requiring formal clearance from the Department.

Please keep in mind that the PAR Form linked below must still be submitted for every change request, delegated and non-delegated

  • The Department will then issue written confirmation regarding whether the PAR is delegated or not before any changes can proceed.

  • All interventions must continue meet Towns Fund value for money requirements.

We have publicly committed to a 20 working-day turnaround for any PAR decisions that are not delegated to get projects off the ground and allow for a quicker response to any delivery issues. All PAR Forms should be submitted to towns.fund@communities.gov.uk CC’ing in your dedicated Cities and Local Growth Unit Area Lead for information.